TL;DR
Wallonia’s regional authorities ordered Google to halt construction at its Farciennes data centre, citing a three-hectare building they say lacked proper planning permission. Google says work is paused while it awaits guidance; it has challenged a separate refusal of its proposed water-cooling permit, with a court hearing scheduled for January.
Wallonia’s regional authorities have ordered Google to stop construction at its data centre in Farciennes, saying a three-hectare building was built without the required planning permission. Google says work is paused while it awaits further guidance. The order puts the project’s permits under scrutiny as the company contests a separate decision rejecting its request to use water from the River Sambre for cooling.
Regional inspectors visited the site on Thursday and told Google representatives to halt construction, the Walloon regional authority said. A regional spokesman described the alleged violation as the construction of a building covering three hectares without proper permission. The order concerns that building, not the entire data-centre site, which is on a former mining area covering about 50 hectares, according to AFP.
The regional order follows a dispute over a proposed change to the project’s cooling system. The original plan called for air cooling, Belgian media reported, but Google later sought permission to use water from the nearby Sambre. Walloon authorities rejected that application over the summer. AFP reported that drought conditions since spring had intensified concern about taking water from the river.
Google told the BBC it had paused work in Farciennes “pending additional guidance” and said it remained “committed to complying with local laws.” The company has challenged the refusal of its water-cooling application in court, AFP reported, with a hearing scheduled for January. The planning-permission dispute and the court challenge are related to the same project, but the available reports do not establish that the court hearing will decide whether the building can remain or be completed.
Stop-work order · court hearing pending
How a cooling plan became a stop-work order
At the heart of the row is water: how the computers are cooled, and where the water comes from.
- The planAir coolingThe original project planned to cool the computers with air, Belgian media reported.
- The changeRiver waterGoogle applied to cool the site with water from the nearby River Sambre.
- SummerRequest refusedAfter a dry spring, regional officials refused the change. Google went to court.
- This weekStop-work orderInspectors told Google to halt building. Officials call it a major offence.
- NextCourt in JanuaryGoogle says it paused the works and will follow local laws.
- Blue: the former mining site, some 50 hectares.
- Orange: the building of three hectares that officials say lacks proper permission.
Sources: AFP, as published by Arab News, November 27, 2026; BBC News, November 29, 2026. Schematic.
Graphic: Powered by Thorsten Meyer AI
Permits Can Delay Data Centre Capacity
The order shows how planning approval and local resources can affect data-centre construction, including projects designed to support cloud computing and artificial intelligence. A stop-work instruction can delay a build while authorities and the company resolve whether the work complies with permits. The reports do not specify the length of any delay or its financial cost.
The water issue adds a local resource question to the planning dispute. Cooling systems remove heat generated by data-centre equipment, but the source material gives no estimate of how much water Google proposed to use at Farciennes. The rejection came amid concerns about drought, according to AFP. That makes the dispute relevant to residents and water authorities as well as to Google and its contractors.
For customers and businesses using cloud or AI services, a delay at one site does not by itself establish a disruption to existing services. It may, however, affect when planned capacity becomes available. The reports provide no evidence of an impact on Google’s current services, and the outcome at Farciennes remains unsettled.
Products Worth Considering

Anker SOLIX C1000 Gen 2 Portable Power Station

DJI Osmo Mobile 7P 3-Axis Smartphone Gimbal with Mic Mini Transmitter, Infinity Black

Apple MacBook Air 13-inch Laptop with M5 Chip, 32GB Memory, 1TB SSD, Silver
As an affiliate, we earn on qualifying purchases.
How the Farciennes Dispute Developed
Google’s proposed facility is on a former mining site in southern Belgium. The building named in the regional authority’s allegation covers three hectares; AFP puts the wider site at about 50 hectares. Those figures describe different areas: the stop-work order concerns the building identified by officials, not the full site.
Greenpeace Belgium said in a report published the week of the order that drone footage showed construction continuing. The group said the latest version of the planning permission had been revoked in August. That is the campaign group’s account; the regional authorities separately said inspectors visited the site and issued an instruction to stop work. The order itself was not located online by the source report, so the precise legal terms are not independently available in the material provided.
The dispute is part of a wider debate about the local impacts of data centres. The BBC reported that Belgium has 54 data centres, citing Data Center Map, and described growing opposition over the facilities’ energy use. AFP also reported that Finnish authorities halted work at two Google data-centre sites in October. Those cases do not establish that the projects share the same legal or environmental issues.
“We have operated in Belgium for over 15 years and remain committed to complying with local laws.”
— Google, in a statement reported by the BBC
Permit Dispute Still Unresolved
The available reporting does not include the text of the stop-work order or independently establish the legal status of every part of the construction. Wallonia says the building lacked proper permission; Google says it has stopped work while awaiting guidance. Whether the building can be legalised, altered or completed later is not clear.
It is also uncertain what the January court hearing will cover and when a decision may follow. The reports do not quantify the proposed water use, say whether another cooling arrangement is under consideration, or indicate how long the halt may last. Greenpeace’s account that work continued after permission was revoked remains an attributed claim, rather than a judicial finding.
January Hearing and Permit Guidance
The next reported milestone is the court hearing scheduled for January on Google’s challenge to the refusal of its water-cooling application. The source material does not give a hearing date or say when the court is expected to rule. Google’s statement indicates construction remains paused pending additional guidance, while Wallonia’s stop-work instruction is in effect according to the reports.
Further clarity will depend on the court proceedings and on any direction from regional authorities about the planning permission and the work covered by the order. Until those steps are reported, the status of the building, the longer-term cooling plan and the construction timetable remain open.
Key Questions
Why did Wallonia order Google to stop construction?
Regional authorities said a three-hectare building lacked proper planning permission. Inspectors visited the Farciennes site and told Google representatives to halt construction, according to the regional authority.
Has Google stopped work?
Google told the BBC it had paused work pending additional guidance. The reports do not provide a timetable for restarting construction.
What is the dispute about water?
Google sought permission to change from the project’s planned air cooling to cooling using water from the River Sambre. Walloon authorities rejected the request over the summer amid reported concerns about drought. The proposed volume of water is not stated in the source material.
What happens next?
Google has challenged the refusal of its water-cooling application in court, and a hearing is scheduled for January. The reports do not specify whether that hearing will resolve the separate question of the building’s planning status.
Source: ThorstenMeyerAI.com